DPP implementation: an 8-step readiness plan

From legal scoping to scaled rollout — the sequence that works.

Key takeaways

  • ●Start with scope and data ownership, not software.
  • ●Supplier data is usually the longest lead-time item.
  • ●Pilot with real missing-data cases before you scale.

The eight steps

  • 1. Confirm legal scope — product families, markets, applicable laws and dates.
  • 2. Assign the responsible operator, programme owner and data owners.
  • 3. Map existing data in ERP, PLM, PIM, LCA tools and supplier files.
  • 4. Run a field-level gap assessment and plan supplier collection.
  • 5. Decide granularity, identifiers, carriers and access policies.
  • 6. Pilot representative products, including missing-data cases.
  • 7. Test scans, permissions, updates, exports and lifecycle handovers.
  • 8. Scale with monitoring, evidence retention and exit/continuity provisions.

Typical timeline

PhaseDuration (indicative)
Scoping & gap analysis1–3 months
Supplier data collection3–12 months
Pilot1–3 months
Rollout3–9 months

Lesson from batteries

Volvo and Circulor's EX90 battery passport took more than five years of development — publishing a passport is quick; establishing the supply-chain visibility behind it is not.